作业帮 > 英语 > 作业

How the budget is check when we assign PM Order to WBS?Does

来源:学生作业帮 编辑:拍题作业网作业帮 分类:英语作业 时间:2024/04/23 20:26:09
How the budget is check when we assign PM Order to WBS?Does the budget check at WBS element?
Elle, the availability control (budget check) occurs at the WBS element. When a budget value is present at a WBS, the WBS becomes a controlling element for the budget check, i.e. if you only budget at the level 1, the level 1 controls the entire structure. If you budget at the level 2's, each is a controlling element. Any linked object, such as a PM order then becomes subject to the budget check.Hope this helps!Bill 查看原帖