作业帮 > 综合 > 作业

1.THIS DRAWING IS FOR PROPOSAL PURPOSES ONLY (NOT FOR CONSTR

来源:学生作业帮 编辑:拍题作业网作业帮 分类:综合作业 时间:2024/05/16 21:14:49
1.THIS DRAWING IS FOR PROPOSAL PURPOSES ONLY (NOT FOR CONSTRUCTION).
2.ALL DRIVES TO BE FULLY GUARDED.
3.PAINT COLOR:7-B GRAY STANDARD INDUSTRIAL ENAMEL,OR MATCHING
CUSTOMER SPECIFICATIONS AND COMPATIBLE WITH HENRY FILTERS
PAINTING PROCESS.
4.ELECTRICAL AND/OR PNEUMATIC CONTROL PANEL(S) TO BE SHIPPED
LOOSE WITH FINAL CONNECTIONS TO COMPONENTS BY OWNER / CONTRACTOR.
5.DIRTY AND CLEANT TANK TO BE COVERED AS NOTED ON DRAWING.
6.RAMP TO BE COVERED AS NOTED ON DRAWING.
7.IF APPLICABLE,ANY PERIPHERAL EQUIPMENT LOCATIONS TO BE DETERMINED
BY OWNER / CONTRACTOR.
8.DRAIN PLUGS TO BE INSTALLED LIQUID TIGHT PRIOR TO TANK INSTALLATION.
9.RAMP TO BE REMOVED FOR SHIPPING PURPOSES AND RE-INSTALLED BY
OWNER / CONTRACTOR.THE BASE PLATE,SIDE PLATES,AND SHIPPED LOOSE
ITEMS TO BE WELDED LIQUID TIGHT AND GROUND SMOOTH.
这个问题请大家体现下实力!
1.THIS DRAWING IS FOR PROPOSAL PURPOSES ONLY (NOT FOR CONSTRUCTION).
1 本图纸仅用于投标(或建议书)(不是用于施工的)
2.ALL DRIVES TO BE FULLY GUARDED.
2 所有传动装置都受到完全的保护
3.PAINT COLOR:7-B GRAY STANDARD INDUSTRIAL ENAMEL,OR MATCHING
CUSTOMER SPECIFICATIONS AND COMPATIBLE WITH HENRY FILTERS
PAINTING PROCESS.
3 油漆颜色:7-B 灰色标准工业瓷漆,或者与客户的技术条件所匹配,并与亨利过滤器涂装工艺相兼容
4.ELECTRICAL AND/OR PNEUMATIC CONTROL PANEL(S) TO BE SHIPPED
LOOSE WITH FINAL CONNECTIONS TO COMPONENTS BY OWNER / CONTRACTOR.
4 电气的和/或气动的控制面板要由业主/承包商将与元器件的最后连接松开加以发货(装运)
5.DIRTY AND CLEANT TANK TO BE COVERED AS NOTED ON DRAWING.
5 脏的和干净的储罐(槽)按图纸的注解覆盖
6.RAMP TO BE COVERED AS NOTED ON DRAWING.
6 斜轨按图纸的注解覆盖.
7.IF APPLICABLE,ANY PERIPHERAL EQUIPMENT LOCATIONS TO BE DETERMINED BY OWNER / CONTRACTOR.
7 如果适用,任何外围设备的位置由业主/承包商决定
8.DRAIN PLUGS TO BE INSTALLED LIQUID TIGHT PRIOR TO TANK INSTALLATION.
在储罐(槽)安装前,要安装对液体密封的排水孔塞,
9.RAMP TO BE REMOVED FOR SHIPPING PURPOSES AND RE-INSTALLED BY
OWNER / CONTRACTOR.THE BASE PLATE,SIDE PLATES,AND SHIPPED LOOSE ITEMS TO BE WELDED LIQUID TIGHT AND GROUND SMOOTH.
9 为了发货(装运),斜轨要卸去,并由业主/承包商重新安装.基板、侧板和发货的松弛项目要对液体密封的焊接,并基础平滑.